Wednesday, March 14, 2018

Driving Range Update


Here is a picture update of the progress over the past ten days:


Work began by stripping the sod of existing tee complex.


The largest section of prep work was on the far right side. 



As this is the section that is being raised to accommodate the extension.


 
It took about 3 full days to bring in all the material.  We used the dirt developed from the Maintenance Facility project.


Once the right side began to take shape, stakes were placed to outline the new tee.


 
A view from the main drive to show the amount of material that was brought in.


Picture taken from dead center of the tee on the far right side.



Jim Nagle (our architect) was on property this past Monday to review progress and to address a few tweaks.


Finally on Monday afternoon, the existing putting green and surrounding area was plotted to aid in design purposes of our new putting green.

The overall project remains on schedule.  The remainder of the week will be used to create the cavity of the tee.  Next week, drainage and irrigation will be installed and we should be at the point of adding tee mix towards the end of the week.